European Space Agency
Vega Evolution Launcher – VUS Cryogenic Propellants Loading Interface System Development

Main Contractor : TCE
The objective of this activity is to develop a new cryogenic connection/disconnection system, with the capability of re-ignition and long coasting phase maneuvers, for both LOX and LCH4 propellant lines ( Interstage 2/3).
Performing 3D Models, analyses (FEM, Thermal and CFD), breadboards/system tests (leakeage, pressure drop, thermal, vibration, mechanical load)
Develop the antiicing system and disconection/emergency disconnection system at Launch Vehicle lift-off
Technology level TRL 6
LOX Cryo-connector system
LCH4 Cryo-connector system
FURNANCE AND BAR MILL
Mechanisms, Hydraulic and Pneumatic Systems
Furnace Combustion and Heating Systems
Main Contractor : TCE
Partner : Primetals Technologies, Germany
Location: LISCO, Libya
Modernization of the Furnace raw material supply system
Modernization of all hydraulic and pneumatic systems of the furnace and bar mill
Modernization of Furnace combustion and heating system




FURNANCE AND BAR MILL
Automation and SCADA
Main Contractor : TCE
Partner : Primetals Technologies, Germany
Location: LISCO, Libya
New control system of the metal bar production line. 4 redundant 400H systems, Sinamics DC Master DC frequency converters, WinCC redundant Scada system, SiRoll control software were installed.
Installing of all instrumentation (control valves, transmitters, Flow meters)
Installing of all field sensors ( limit switches, proximity switches, laser sensors, cameras, temperature sensors etc)
Commissioning and Performance : Furnace and Bar Mill
Travelling Cranes 150 – 230 tons (seven traveling cranes)
Main Contractor : Bilfinger Maschinenbau, Austria
Subcontractor : TCE
Location: LISCO, Libya
New automation system including upgrading from analogue drives to digital drives.
Installing a new safety system including anticollision system
Upgrading the electrical system, motors, mechanical equipment and structure from 150 tons to 230 tons
Design, erection and commisioning the new industrial cooling system with ammonia for all 7 traveling cranes




Installing Water Cooled Ducts System for 3 x Furnace
Fume Extraction System
Main Contractor : TCE
Location: LISCO, Libya
Dismantle (Old Straight Duct) (1st) For Each Furnace With Accessories
Install New Parts (3pcs) For Each Furnace & Assembly Of The Old Parts Which Has Been Taken Out
Dismantle (Old Water-Cooled Duct Bend)(2pcs) For Each Furnace With Accessories
Install New Parts (2pcs) For Each Furnace &Assembly Of The Old Parts Which Has Been Taken Out
Dismantle (Old WCD Dec Damper And Combustion Air Dampers , Which Consist Of (1st) For Each Furnace
Assembly And Install New Parts (1st) For Each Furnace With Accessories Which Has Been Taken Out
Heating district Unit 1 Cernavoda Nuclear Power Plant
Main Contractor : ATC-E
Location: Cernavoda Nuclear Power Plant, Romania
Complete automation of the heating district heating point, related to Unit 1, was carried out. The role of automation is to prepare the primary thermal agent that is transmitted to the town of Cernavoda, from the common steam bar of the Nuclear Electrica complex.
The automation system meets nuclear safety standards, being redundant: PLC controller – S7-400H, redundant WinCC servers, redundant Profibus communication, double redundant Profinet communication


Schaeffler
Inline Bearing Roundness Measuring System
Main Contractor : ATC-E
Location: Brasov, Romania
The automation system was designed to increase the quality control of the bearings produced for the rail industry. Each bearing will have an optical measure of roundness and roughness, with a precision of 1 micron. The whole system will generate quality control sheets for each analyzed benchmark, otherwise the quality of the products will have full traceability.
Arcelor Mital
Blast Furnace no 5 Automation Control System
Main Contractor : ATC-E
Location: Romania
The automation project was a complex one and aimed at the management of metal production, from metal ore. The supply limit of the programmable automaton was the furnace temperature monitoring and the ore agglomeration system. Over 2000 temperature sensors were used and an efficient solution was implemented for the agglomeration part, using a single S120 frequency converter that manages 8 agglomeration bands.


OMV Petrom
Water injection pumps – automation control system
Main Contractor : ATC-E
Location: Poieni, Romania
Complete automation of the technological water injection system in the crude oil deposit was achieved. The automation maintained a constant water flow, a constant pressure, which allowed the extraction of crude oil. The old cylinder pumps were replaced with centrifugal pumps. The purpose of the automation system was to provide a closed-loop control application for water injection at OMV-Petrom Depozit 9 Poieni. The use of EX converters determined the injection of water into the crust, with variable flow in complete safety.